How to demolish a warehouse or production hall?



According to the rules in force in the construction industry, the demolition of the building requires a similar permit as for construction. A demolition log is also kept similar to the construction log. The disassembly of the industrial hall itself is also not a simple task, because it is carried out in stages that are in line with the schedule. How to safely demolish a production or warehouse hall?

Pre-demolition stage
Warehouse and production halls are usually largely built of steel elements. Therefore, the dismantling of such facilities should be carefully planned and carried out according to the plan. There are safety and economic reasons for this, as most of the components are usually reused elsewhere, most often after recycling.

The demolition of halls made of steel elements should be carried out by specialized teams of companies that have experience in both the disassembly of structures as well as the relocation of industrial machines and entire production lines. Sometimes steel elements require professional cutting in such a way that the obtained parts are suitable for both transport and recycling.

At the beginning of each demolition of a production or warehouse hall, it must be completely disconnected from utilities such as electricity and water, and lamps, fixtures, sanitary devices and all accessories that are not damaged enough that they cannot be used elsewhere.

Before the demolition itself, it is good to remove the wall cladding and roofing.

Demolition of the load-bearing structure
Proper dismantling of metal halls is the dismantling of load-bearing elements such as beams and columns together with their reinforcing elements. Therefore, it is good to unscrew some connections as far as possible. Demolition should be started from the top, removing the purlins and beams. All the time you should pay attention to the stability of the elements, so that they do not start falling in the wrong direction - of course with the appropriate degree of caution.

During the demolition of tall structures, mobile cranes are used, which safely transport the unassembled elements to another place. When dismantling lower elements and floors, excavators and loaders can be used. The demolition site should be properly marked and preferably fenced. All this to limit the number of bystanders. Demolition cannot be carried out when the wind force is greater than that allowed in the design.