Microsoft Project: Predecessors & Successors Examples

Microsoft Project is a robust project management tool that aids in planning, organizing, and managing projects of all sizes. With its inclusivity of predecessor and successor tasks, it ensures logical flow and smooth execution. Let's explore the concepts of predecessor and successor tasks in Microsoft Project with practical examples.

Displaying The Task Path In Microsoft Project
Displaying The Task Path In Microsoft Project

Before delving into the examples, let's understand these terms. Predecessor tasks are those that must be completed before the current task can begin, while successor tasks start once the current task is done.

The Top 10 Microsoft Project Scheduling mistakes
The Top 10 Microsoft Project Scheduling mistakes

Predecessor Tasks

Predecessor tasks ensure chronology in your project by establishing a clear sequence of tasks. They are indicated in the task dependencies section of the task information dialog box.

Ten useful, but little known features in Microsoft Project
Ten useful, but little known features in Microsoft Project

To set a predecessor, highlight the task, go to the "Task" tab, click "Predecessors," then choose the predecessor task and the type of dependency (Finish-to-Start is the most common).

Finishing Before Starting

Microsoft Project progress | How to show progress lines [step by step]
Microsoft Project progress | How to show progress lines [step by step]

A common predecessor type is Finish-to-Start (FS). In this case, the successor task can't start until the predecessor task is 100% complete. For example, construction of a building wall (predecessor) must complete (finish) before painting the wall (successor) can start.

In Microsoft Project, a task with an FS predecessor would look like this: Task B (Start: Finish of Task A).

Starting After Completion

Microsoft MS Project Training Courses in London and UK
Microsoft MS Project Training Courses in London and UK

Another predecessor type is Start-to-Finish (SF). Here, the successor task must wait until the predecessor task begins before it can end. An example would be waiting for raw materials to arrive (start) before production (end) can complete.

In Microsoft Project: Task A (Finish: Start of Task B).

Successor Tasks

the project 2010 managing complexity poster
the project 2010 managing complexity poster

Successor tasks are crucial in managing resources and maintaining project momentum. They depend on the completion of predecessor tasks. If a predecessor task is delayed, it can ripple through the project, affecting successor tasks.

To set a successor, again use the "Predecessors" option in the "Task" tab. Once the predecessor is chosen, ensure to select the 'Successor' option in the "Type" column.

Microsoft Project and Effort Driven Tasks
Microsoft Project and Effort Driven Tasks
Microsoft Project - Full Tutorial for Beginners in 13 MINUTES!
Microsoft Project - Full Tutorial for Beginners in 13 MINUTES!
Getting Started With Microsoft Project 2010
Getting Started With Microsoft Project 2010
Microsoft Project 2019 Tutorial - 5 Hour MS Project Course for Beginners!
Microsoft Project 2019 Tutorial - 5 Hour MS Project Course for Beginners!
Microsoft Project - Tutorial for Beginners in 14 MINUTES!  [ COMPLETE COURSE ]
Microsoft Project - Tutorial for Beginners in 14 MINUTES! [ COMPLETE COURSE ]
Project Report Explained | Concept, Features & Components (Easy Notes)
Project Report Explained | Concept, Features & Components (Easy Notes)
Ten useful, but little known features in Microsoft Project
Ten useful, but little known features in Microsoft Project
Ten useful, but little known features in Microsoft Project
Ten useful, but little known features in Microsoft Project
Simplified Project Portfolio Management - FluentPro Software
Simplified Project Portfolio Management - FluentPro Software
How to Import a Microsoft Project Schedule Into Project for the Web
How to Import a Microsoft Project Schedule Into Project for the Web
STOP Using Only Microsoft & Google 😳 Try These Better Alternatives!
STOP Using Only Microsoft & Google 😳 Try These Better Alternatives!
Microsoft Project Automation & Customization | Ms Project Advance Template | Milestone tracking | CPM Critical Path
Microsoft Project Automation & Customization | Ms Project Advance Template | Milestone tracking | CPM Critical Path
Microsoft Project Review: Features, Pros & Cons
Microsoft Project Review: Features, Pros & Cons
Introduction to Microsoft Project 2019 | dummies
Introduction to Microsoft Project 2019 | dummies
an excel spreadsheet with multiple columns and numbers in the top row, including
an excel spreadsheet with multiple columns and numbers in the top row, including
How to Use Microsoft Project for Beginners
How to Use Microsoft Project for Beginners
How to Create Master Project, SubProject in Microsoft Project 2010
How to Create Master Project, SubProject in Microsoft Project 2010
Using Microsoft Project's Task Notes
Using Microsoft Project's Task Notes
Project Plan Presentation Ideas for Effective Team Workflow
Project Plan Presentation Ideas for Effective Team Workflow
How does Planner compare to MS Project?
How does Planner compare to MS Project?

Starting After Completion

Similar to predecessors, Finish-to-Start (FS) is the most prevalent successor type. This means the successor task starts as soon as the predecessor task is finished. An example is installing flooring (successor) only after painting (predecessor) is completed.

In Microsoft Project: Task B (Start: Finish of Task A).

Finishing Before Completion

Start-to-Start (SS) successors are less common. Here, the successor task must start before or at the same time as the predecessor task. For instance, both setting up a booth and organizing event logistics must start simultaneously. To do this, pleasure both tasks on the same baseline.

In Microsoft Project: Task B (Start: Start of Task A).

Microsoft Project's predecessor and successor tasks ensure project integrity and timeline adherence. It's essential to understand their functioning and productivity implications. Hence, it's recommended to regularly review task dependencies to avoid bottlenecks and ensure smooth project flow.