Estimating material costs, so let's talk about how materials are priced. Although

00:06.100 --> 00:09.820
materials may be installed by a given unit of measure, it may need to be

00:09.820 --> 00:14.020
purchased with a different unit of measure. And here's some examples, concrete.

00:14.020 --> 00:20.140
Ready mixed by the pound in various size sacks, or you can have it pre-mixed and

00:20.140 --> 00:25.780
have it purchased by the cubic yard. Lumber. Lumber pricing is ultimately

00:25.780 --> 00:30.100
established in board feet, even though you may be purchasing 1,000 feet of 10

00:30.100 --> 00:36.480
foot studs. To define what a board foot actually is, it's 1 inch by 12 inches by

00:36.480 --> 00:42.020
12 inches and that equals 1 board foot. Board feet or BF is a volume unit of

00:42.020 --> 00:46.940
measure. Gypsum board. It's purchased by the square foot per sheet size

00:46.940 --> 00:52.620
increments and installed by the square foot. Plaster. Plaster is purchased by

00:52.620 --> 00:58.340
the pound in various sacks sizes and it's installed by the square yard. Painting

00:58.340 --> 01:02.380
is priced by the gallon and installed by the square foot. It's important to know

01:02.380 --> 01:06.540
when you look at your painting is understand what the absolute cost is per

01:06.540 --> 01:11.780
square foot for all required coats. So to recap on material costs, make sure that

01:11.780 --> 01:16.140
you understand clearly what's required for purchasing, including the unit of

01:16.140 --> 01:21.860
measure and the unit sizes required for individual purchases. You also need to

01:21.860 --> 01:25.820
understand that purchasing materials is going to require different quantities

01:25.820 --> 01:30.220
compared to your labor. We'll talk about that more as we move on into the

01:30.220 --> 01:34.700
estimating process of how to price out your material cost quantities versus

01:34.700 --> 01:37.980
your labor cost quantities.