So now let's talk about what to include and exclude on an estimate cover sheet.

00:04.560 --> 00:08.880
It's always a good practice to create a cover sheet, having all general information of

00:08.880 --> 00:14.040
the estimate regardless of whether or not it's required as a bid proposal or a bid form

00:14.040 --> 00:15.720
that needs to be filled out.

00:15.720 --> 00:18.600
So start by identifying what the scope of the project is.

00:18.600 --> 00:23.440
The self-explanatory cover sheet or client provided bid form for the estimate should be used

00:23.440 --> 00:26.360
to include the following information at a minimum.

00:26.360 --> 00:30.520
Now keep this in mind that even if it's not required, it's beneficial to have some

00:30.520 --> 00:34.880
sort of a cover sheet for your estimate so that it could be understood if it's looked

00:34.880 --> 00:40.040
at three months from now or six months or a year from now, it has to still make sense.

00:40.040 --> 00:42.680
So here we have a project name and location.

00:42.680 --> 00:47.360
The location is important here, which helps identify if there's any related travel costs

00:47.360 --> 00:51.600
or different city cost indexes that may have been applied to the estimate.

00:51.600 --> 00:53.440
Very important include a proposal date.

00:53.440 --> 00:55.560
What date was it submitted to the client?

00:55.560 --> 01:00.320
Because very often these prices are only good for 30 days or 60 or 90 days.

01:00.320 --> 01:04.640
Make sure you identify that in your proposal, but include a proposal date.

01:04.640 --> 01:05.880
Client company name.

01:05.880 --> 01:10.320
This is the full name of the client or company name that you're bidding the work to.

01:10.320 --> 01:14.160
In addition to the client company name, make sure that it includes the contact information

01:14.160 --> 01:16.360
including phone address, etc.

01:16.360 --> 01:21.000
In addition, include the estimator's name of the project, the name and your company,

01:21.000 --> 01:22.760
along with the estimate amount.

01:22.760 --> 01:27.680
The scope will work and I'm noting here to specify the trades and spec sections if you're

01:27.680 --> 01:29.000
a subcontractor.

01:29.000 --> 01:34.240
So therefore your scope would be limited, perhaps to plumbing or electrical or rough carpentry.

01:34.240 --> 01:39.640
As a general contractor, the scope may identify that is building number two, phase one or whatever

01:39.640 --> 01:42.760
that may be for plans and specifications dated.

01:42.760 --> 01:43.760
This is vital.

01:43.760 --> 01:48.920
You are given a set of bid documents to work off of to provide your pricing needs be identified

01:48.920 --> 01:54.640
carefully with the actual plan date and any specifications and also if there's any

01:54.640 --> 01:56.600
adenums associated with them.

01:56.600 --> 02:02.520
Provide any inclusions if applicable, any exclusions, alternates and assumptions.

02:02.520 --> 02:04.880
These may not always be available on the bid form.

02:04.880 --> 02:08.720
They might not actually have any room for that, but if there's a place to identify that

02:08.720 --> 02:13.000
or actually add a separate page, include those if acceptable.

02:13.000 --> 02:18.040
Keep in mind that exclusions are sometimes not allowable within a bid form.

02:18.040 --> 02:21.440
So understand your bid form and what the limitations are for that.

02:21.440 --> 02:25.420
If it's an negotiated job or a client that you're working directly with, then you actually

02:25.420 --> 02:30.800
have a liberty to go ahead and identify inclusions and exclusions and perhaps even an exclusion

02:30.800 --> 02:35.680
but then you could also provide an alternate or an add-on amount for that if it's unclear

02:35.680 --> 02:37.640
whether or not it's going to be required.

02:37.640 --> 02:42.400
And what I mean by assumptions is if something's unclear on the bid documents that are not

02:42.400 --> 02:47.280
clearly identified, that's where you make an assumption because for example you know that

02:47.280 --> 02:50.760
this is going to be extra repayment on the outside of the building, but you don't know

02:50.760 --> 02:54.960
what type it may be so you could verify what the assumption is that we're going to use

02:54.960 --> 02:58.480
colored concrete and it might be scored every so many feet.

02:58.480 --> 03:01.520
That could be a fair assumption of what's going to be installed on the outside.

03:01.520 --> 03:03.280
That's included in your price.

03:03.280 --> 03:07.240
So it helps validate the scope of work that you're priced at in your estimate to the client.