What I'd like to bring to your attention, too, are these symbols that are right here.

00:06.440 --> 00:12.400
You can see that it's saying 1 over a 4.3.

00:12.400 --> 00:21.080
I have 2 over a 4.1, 1 over a 4.1, and another symbol over here and 1 here.

00:21.080 --> 00:23.560
This is a floor plan.

00:23.560 --> 00:28.920
So this is a horizontal slice through the building.

00:28.920 --> 00:36.520
These symbols here with the polyline following down from there are saying if you want to

00:36.520 --> 00:45.380
look at the building section that is cut through the building right here, go look on sheet

00:45.380 --> 00:48.920
a 4.1, look at image 2.

00:48.920 --> 00:53.080
So what I'm going to do very quickly is I'm just going to zoom back and then I'll tab

00:53.080 --> 00:58.520
down and you can see that here is sheet a 4.1.

00:58.520 --> 01:02.760
I have image 1 and I have image 2.

01:02.760 --> 01:11.200
So these pages are vertical slices through the building cut at particular locations.

01:11.200 --> 01:20.160
So again, if I go back to my basement plan, you can see that I have 3 vertical sections

01:20.160 --> 01:24.040
and 2 horizontal sections.

01:24.040 --> 01:30.080
These horizontal sections we call longitudinal sections because they're the longer part

01:30.080 --> 01:31.400
of the building.

01:31.400 --> 01:37.360
We call these other sections transverse because they're going through the shorter part of

01:37.360 --> 01:38.360
the building.

01:38.360 --> 01:41.280
So again, I have the floor plan.

01:41.280 --> 01:43.680
We've come in through the garage.

01:43.680 --> 01:45.600
We understand dimensions.

01:45.600 --> 01:47.360
We have the keynotes.

01:47.360 --> 01:53.600
I come into the mudroom, I go up a couple of steps and I'm now at this hallway meeting

01:53.600 --> 01:54.600
area.

01:54.600 --> 01:58.120
I have an elevator shaft over here.

01:58.120 --> 02:06.600
What you can see is that I also have a call out that says 1 over D7.2.

02:06.600 --> 02:09.080
So I have the symbol.

02:09.080 --> 02:16.160
I have the lines that are connecting to a heavier polyline that goes around the elevator

02:16.160 --> 02:17.160
shaft.

02:17.160 --> 02:25.160
What this symbol is saying is that when I want to see the enlarged plan of this area to

02:25.160 --> 02:30.320
go to image 1 on page D7.2.