WEBVTT

00:00.000 --> 00:05.000
So now let's talk about validation and methods for checking for errors.

00:05.000 --> 00:10.000
So by starting to validate the actual scale on your drawings where you do your takeoff,

00:10.000 --> 00:14.680
your quantity takeoff, make sure the scales are correct because if your quantities are

00:14.680 --> 00:19.000
off, if your scale is off, the whole estimate will be off.

00:19.000 --> 00:22.680
Let's start this by verifying that all drawing scales are correct.

00:22.680 --> 00:25.560
Test any noted scales to a known dimension.

00:25.560 --> 00:29.640
And typically what I do is I use the largest dimension available.

00:29.640 --> 00:33.080
Because it might only be the height of a doorway that you know is eight foot, then that's

00:33.080 --> 00:34.080
suitable enough.

00:34.080 --> 00:38.680
But if you actually have a dimension from column to column that'd be even greater because

00:38.680 --> 00:44.400
that's looking like 25 or 30 feet or so, it makes your adjustment much more accurate

00:44.400 --> 00:46.320
when calculating that.

00:46.320 --> 00:49.560
Accuracy improves when the longest dimensions are tested.

00:49.560 --> 00:55.200
All digital takeoff software programs are just as vulnerable to reduced size drawings.

00:55.200 --> 01:00.120
To remedy this, they have the advantage of calibrating the actual scale.

01:00.120 --> 01:05.360
If you're doing the takeoff manually, you may have to use a different scale altogether.

01:05.360 --> 01:10.520
For example, if it says that it's quarter inch and the scale correction is half inch, you'll

01:10.520 --> 01:16.440
have to use a different size scale to measure those dimensions or objects on your drawings.

01:16.440 --> 01:20.040
So as you're checking the scale on your drawings and making sure that your takeoff was done

01:20.040 --> 01:24.680
accordingly, go ahead and double check everything else that's associated with actual cost

01:24.680 --> 01:28.880
or counts would have you, and that would include your door schedules, might include your

01:28.880 --> 01:29.880
wall types.

01:29.880 --> 01:33.920
Anything as a double check always benefits the entire project.

01:33.920 --> 01:36.840
After a while, you'll see that you might have four or five items that you'll always

01:36.840 --> 01:41.480
check which would include your scale and make sure that you test these on a regular basis.

01:41.480 --> 01:47.080
The more you estimate, the more you'll identify some costs that might be out of whack.

01:47.080 --> 01:51.560
As an example, as you're using a wrong scale, perhaps your scale is half of what it should

01:51.560 --> 01:57.440
be, you should be able to get a gut feeling as to the quantities are not matching up.

01:57.440 --> 01:59.640
They don't seem right.

01:59.640 --> 02:03.640
Another good example is when you identify your drawings, it'll probably tell you how

02:03.640 --> 02:07.160
large the site or how large the building area is.

02:07.160 --> 02:10.800
If you do a double check on all your building areas or all your site areas, it should

02:10.800 --> 02:14.040
marry up or match up to what's actually shown on the drawings.

02:14.040 --> 02:18.600
These double checks are great to validate your estimates to yourself and the management

02:18.600 --> 02:18.920
team.