Welcome back to the VDCI video course content for Reva MEP for plumbing.

00:05.040 --> 00:08.600
In the previous video, we went ahead and took some time to take a look at a sample project

00:08.600 --> 00:13.000
just to kind of get our heads wrapped around plumbing scope of work and how it kind of

00:13.000 --> 00:14.000
works.

00:14.000 --> 00:15.000
And I still have that open here.

00:15.000 --> 00:16.000
I'm going to go ahead and close it.

00:16.000 --> 00:19.480
So since you might have been jumping between different views, those kind of things, let's

00:19.480 --> 00:24.080
go ahead and use the close in or close windows here up at the top.

00:24.080 --> 00:26.840
This will go ahead and close any inactive windows.

00:26.840 --> 00:29.840
And you should have possibly two files open.

00:29.840 --> 00:33.480
So this button will close any windows, but it will not close a file completely since

00:33.480 --> 00:37.040
we had our project open previously to opening this file.

00:37.040 --> 00:38.360
This one stays open.

00:38.360 --> 00:42.360
So I'm going to switch over to my plumbing model here, which is my bin 322.

00:42.360 --> 00:44.640
And I'm going to go ahead and just close out of this.

00:44.640 --> 00:46.160
Don't worry about saving anything.

00:46.160 --> 00:47.640
You don't need to.

00:47.640 --> 00:48.640
Great.

00:48.640 --> 00:54.120
So you should be back in your bin 322 file with your name and really kind of where do you

00:54.120 --> 00:55.120
want to start with plumbing?

00:55.120 --> 00:57.800
I mean, there's a couple of different locations that we could start.

00:57.800 --> 01:06.120
We could determine the point of contact where items are going to be coming in.

01:06.120 --> 01:08.880
We could determine that and start running our sanitaries.

01:08.880 --> 01:14.040
We could have our equipment and our water heaters and start creating our distribution system

01:14.040 --> 01:16.880
for the hot and cold water.

01:16.880 --> 01:18.560
There's many different locations.

01:18.560 --> 01:20.480
We could put in the fixtures, right?

01:20.480 --> 01:21.480
We need fixtures.

01:21.480 --> 01:27.280
A lot of times, you know, in the previous sample model that we looked at, we went ahead

01:27.280 --> 01:31.000
and you noticed that they didn't actually have the fixtures there when I turned off

01:31.000 --> 01:32.240
the model.

01:32.240 --> 01:39.400
That is because they did not copy monitor or place their own fixtures in the file.

01:39.400 --> 01:41.560
They just use the architectures as a background.

01:41.560 --> 01:45.120
They did have some fixtures with regards to like the washer machine boxes, things like

01:45.120 --> 01:49.320
that, but they didn't have like the toilets in the sinks and the lavatories and those

01:49.320 --> 01:51.320
kind of things.

01:51.320 --> 01:56.280
In our instance, we're going to kind of start with just kind of a general point of contact

01:56.280 --> 02:02.080
or point, we'll start off with the water system kind of coming into the building and putting

02:02.080 --> 02:04.240
in some families.

02:04.240 --> 02:07.400
What I want to go ahead and do is we're going to place our first pipe.

02:07.400 --> 02:11.880
So, on my level one plumbing here, what I'm going to do is we're going to say, and again,

02:11.880 --> 02:17.880
traditionally, most of the time, the plumbing engineer would be responsible from the edge

02:17.880 --> 02:20.880
of the building to five feet out.

02:20.920 --> 02:26.000
If you take this and have an edge around the building, they would have that to five feet

02:26.000 --> 02:31.960
out and then that would go ahead and that would be where they would draw their pipe to.

02:31.960 --> 02:36.840
Obviously, they coordinate the elevation of the point of contact, but beyond that five

02:36.840 --> 02:39.040
foot spot, they would go ahead.

02:39.040 --> 02:46.040
That would actually be the part of the civil engineers scope of work to take it beyond

02:46.040 --> 02:47.480
that five foot.

02:47.480 --> 02:50.520
We do have a mechanical room back here, so I'm actually going to go ahead and use that

02:50.520 --> 02:53.600
for our water heaters and everything, and we're going to kind of make it simple.

02:53.600 --> 02:59.320
We're going to say that the water and the storm during or the all the services and everything

02:59.320 --> 03:02.000
are coming in on this side here.

03:02.000 --> 03:05.840
So, to draw our first pipe, I'm going to go to my systems tab.

03:05.840 --> 03:12.000
I am going to go to my pipe, and we're going to say that the water is obviously coming in

03:12.000 --> 03:13.000
underground.

03:13.000 --> 03:15.600
So, pipe type, we have just the standard.

03:15.600 --> 03:16.800
We'll go ahead and use the standard.

03:16.800 --> 03:17.800
Actually, you know what?

03:17.800 --> 03:22.360
We'll create, we'll stick with the standard for right now, and then we'll create kind

03:22.360 --> 03:23.360
of a, no, you know what?

03:23.360 --> 03:24.360
Let's do it right now.

03:24.360 --> 03:26.360
I'm going to go ahead and hit edit type.

03:26.360 --> 03:31.400
I'm going to go ahead and hit duplicate, and let's go ahead and name this copper, just

03:31.400 --> 03:32.400
like what the other one had.

03:32.400 --> 03:34.840
So, we're going to create a copper pipe type.

03:34.840 --> 03:38.520
Now, we've created that pipe type, we could tell you to just go ahead and start using

03:38.520 --> 03:39.520
it.

03:39.520 --> 03:41.480
I'm going to double check our routing preferences, though.

03:41.480 --> 03:44.280
I'm going to come down here to edit.

03:44.280 --> 03:50.040
So our copper, K, boom, these are all fine, we'll use welded, that's fine for right

03:50.040 --> 03:54.160
now, and our pipe segment, that's really what I wanted to check.

03:54.160 --> 03:58.640
Let's say that we don't want to have any copper pipe that's going to be say over, let's

03:58.640 --> 04:04.080
say, or under a half an inch, let's go with a three, actually three quarters.

04:04.080 --> 04:08.080
So make your minimum size three quarters of an inch, your max size here, let's go ahead

04:08.080 --> 04:13.000
and we're not going to have any copper pipe over say six inches, right?

04:13.000 --> 04:18.720
So I'm just, this helps to keep other team members kind of in line so that people aren't

04:18.720 --> 04:22.160
putting pipe sizes that aren't going to be used, but it also just helps shorten the

04:22.160 --> 04:27.520
list of pipe sizes available to pull down from elbow, all the kind of thing, that's all

04:27.520 --> 04:28.520
good.

04:28.520 --> 04:34.760
I'm going to go ahead and okay, and I'm going to go ahead and apply and okay.

04:34.760 --> 04:39.040
Now right now, it's wanting to put, so my pipe type has been changed to copper.

04:39.040 --> 04:41.880
Now it's wanting to put this guy up high, though.

04:41.920 --> 04:43.280
I'm going to change the middle elevation.

04:43.280 --> 04:47.280
I'm going to say I want it to be negative three foot six.

04:47.280 --> 04:50.880
So what that is doing is it's going to put it below my level plan because we're saying

04:50.880 --> 04:53.520
that the water is coming into this room.

04:53.520 --> 04:57.120
It's coming into the building at minus three foot six.

04:57.120 --> 05:00.400
That is like say what civil gave us as that size.

05:00.400 --> 05:02.560
So I also want to check the system type.

05:02.560 --> 05:03.560
I'm going to come here.

05:03.560 --> 05:05.200
I don't want to be hydraulics supply.

05:05.200 --> 05:08.400
I want it to be domestic cold water.

05:08.400 --> 05:12.920
So you want to check your elevation, you want to check your system.

05:12.920 --> 05:16.960
And let's say that this pipe here, this is, let's say for this building, this is going

05:16.960 --> 05:21.600
to be a four inch service coming in because it's a school, need a lot of water.

05:21.600 --> 05:25.400
What I'm going to go ahead and do is I'm going to click here, I'm going to drag down,

05:25.400 --> 05:30.880
click again, and you're like, wait, why, why is nothing being seen?

05:30.880 --> 05:34.200
Remember, we're drawing underground right now.

05:34.200 --> 05:38.080
We have to adjust our view range to be able to see that location.

05:38.080 --> 05:42.760
So I'm going to head escape and I've drawn that piece of pipe and it is there.

05:42.760 --> 05:46.200
If I go to my 3D view, it should be seen.

05:46.200 --> 05:47.440
There it is.

05:47.440 --> 05:53.720
As you can see, I can see my pipe there, but it's not visible in my plan.

05:53.720 --> 05:58.040
I need to adjust the view range of my plan so that I can see that pipe.

05:58.040 --> 06:00.480
I'm going to go to my view range edit.

06:00.480 --> 06:06.240
I'm going to change my view depth to say I can go associate level on, let's say I wanted

06:06.240 --> 06:11.560
to go minus four feet, let's go minus six feet, just in case.

06:11.560 --> 06:15.960
I hit apply and you see my pipe comes up.

06:15.960 --> 06:19.040
Now what's the difference here between the primary range and the view depth?

06:19.040 --> 06:24.640
Well, if I hit apply and I hit OK, notice how I can still select on this, but if I drag

06:24.640 --> 06:32.720
a window over it, notice how it does not select and that's because it is not in my primary

06:32.720 --> 06:34.160
range.

06:34.160 --> 06:39.080
So if I wanted to be able to drag a window to select that, I'd need to set the primary,

06:39.080 --> 06:44.920
the bottom of my primary range, so let's say like negative four feet, I'm encompassing

06:44.920 --> 06:53.320
that negative three foot six I did, hit apply, hit OK, and now I can select it as that,

06:53.320 --> 06:55.520
but I could always just click on it if I want to.