Sizewell B: The facts

Last edited 14 October 2002 at 8:00am
Sizewell nuclear power station

Sizewell nuclear power station

Location: Near Leiston, Suffolk, on the East Anglian coast

Reactor Type: Pressurised Water Reactor (PWR)

Electrical Output: 1188 MW

Number of Reactors: One

Annual energy generated (2001): 9.7 TWh (a mere 10% of what could be produced from wind power offshore of East Anglia alone)

Estimated amount of highly radioactive spent fuel produced to date: 210 Tonnes

Escalation of construction costs (in 1991 prices):

Original estimate: £1,982 million

1987: £2,141 million (13% rise)

1989: £2,353 million (24% rise)

1990: £2,566 million (35% rise)

1991: £2,648 million (40% rise)

Start of generation: 1995

Built: 1988 - 1995

Decision to build: 1987

Planning inquiry: 1983 - 1985

 

 